his year has been an exciting and productive one for the oil and gas industry. Headlining developments include first oil at two separate projects.
At the time of the September announcement, Pikka was producing approximately 40,000 barrels of oil per day gross, and Santos Managing Director and CEO Kevin Gallagher said of the development, “With pressure support now established and wells coming online progressively, we continue to target plateau production rates at the end of the third quarter of 2026.”
In mid-August, ConocoPhillips Alaska announced first oil—under budget and ahead of schedule—at its Coyote 3SX development on the Kuparuk River Unit (KRU). The approximately $800 million project began construction in early 2026, and its expected peak oil rate is 12,000 barrels per day gross.
Unlike Pikka, which is a new development that will support further expansion in coming years, Coyote 3SX leveraged existing infrastructure and “efficiently brings new production online in the KRU while supporting Alaska jobs, strengthening throughput in the Trans Alaska Pipeline System,” according to a company statement. At the time of the announcement, ConocoPhillips Alaska President Erec Isaacson said, “Coyote 3SX demonstrates our commitment to maximizing the value of our legacy assets while continuing to deliver safe, reliable domestic production… The additional pipeline required for the project will support increased production from Coyote as volumes rise in 2026 and beyond.”
In 2025, HEX upgraded the Julius R platform and renamed it Allegra Leigh; it also brought online two new gas wells and reworked an existing well in the Kitchen Lights Unit, returning it to production.
In June, HEX rebranded Furie to HEX Operating, and HEX’s other subsidiary, HEX Cook Inlet, is now HEX Energy. According to the company, the rebranding reflects the company’s evolution and long-term strategic direction while creating a consistent identity across the HEX family of companies. In June, Hendrix said that, while the names and visual identity of HEX are evolving, the company’s core commitments to safety, operational excellence, teamwork, and community stewardship remain unchanged.
The acquisition also included 75,000 net acres in the Grey Owl unit south of Badami and additional non-unitized acreage in between them, bringing APA Corporation’s total acreage on the North Slope to approximately 487,000 gross acres.
One of the most active bidders, North Slope Exploration, a Colorado-based unit of Armstrong Oil and Gas, won leases on seventy-eight tracts southwest of Teshekpuk Lake. ConocoPhillips successfully bid on thirty tracts adjacent to its current positions. Repsol and Shell affiliates, bidding together, won a section of forty-two tracks south of Teshekpuk Lake. ExxonMobil focused its bids on twenty-four tracts close to Teshekpuk Lake.
Other bidders included Santos affiliate Oil Search and smaller players Beacon, Epoch, SE Partners, and Peritas.
Winning bids totaled $163.7 million for 187 tracts, and Alaska received approximately $80 million as its 50 percent share of the proceeds. “Investor confidence in Alaska’s energy future is not only strong—it’s growing,” said Steve Wackowski, president and CEO of the Alaska Oil and Gas Association in March. “That confidence is critical to advancing responsible development of Alaska’s vast resources, supporting jobs, sustaining the Trans Alaska Pipeline System, and strengthening US national security in an increasingly uncertain world.”
HEX outbid AIDEA for the southernmost tract offered, a movement away from its operations in Cook Inlet, a significant expansion for the company. “This acquisition reflects our long-term confidence in Alaska and our commitment to developing energy opportunities with discipline, local knowledge, and respect for the regulatory process,” said HEX President and CEO John Hendrix in June.
The five winning bids resulted in receipts from HEX and AIDEA totaling $3.7 million, and Alaska receives 50 percent (nearly $2 million) from the sale, according to BLM.
One novel solution has been proposed by Cook Inlet LNG, in partnership with Glacier Oil & Gas, which operates the onshore West McArthur River Unit and the offshore Osprey platform in the Redoubt Unit. The two companies envision bringing a floating storage and regasification unit to Cook Inlet. The unit would be moored along the Osprey platform, with mooring anchors placed on the seafloor. The unit would be resupplied by LNG tankers every thirty to forty-five days during winter and less often during summer months, with the intent to make up for anticipated shortages in gas supply in the coming years. Cook Inlet LNG is in the process of obtaining regulatory approvals, and if approved the project is anticipated to begin supplying gas to Southcentral in mid-2029.
Hilcorp and HEX, the region’s largest and second largest producers, respectively, continue to invest in more traditional methods of producing natural gas in Cook Inlet. Hilcorp is planning two new grassroots wells targeting the Beluga gas sands and one sidetrack well.
HEX has invested heavily in Cook Inlet, and two of its wells were the top natural gas producers in the region in 2025. HEX invested $30 million in Cook Inlet operations in 2025 and more than $50 million in 2026 to drill two new wells, reinvest in platform modifications, and partner with Fortune Sea Alaska to secure Cook Inlet’s newest and largest vessel, Atlantis, to service offshore platforms.
HEX is more than tripling its commitment to heating Southcentral, signing a firm contract with ENSTAR Natural Gas Company to provide 25 million cubic feet of natural gas per day. At the August conference, Hendrix said the commitment will increase to 29 million cubic feet per day in 2028, but there are no set commitments after that. ENSTAR’s owner, TriSummit Utilities, reports that ENSTAR delivers about 33 billion cubic feet of natural gas each year to customers, or about 90 million cubic feet per day on average, with summer lows and spikes up to 230 million cubic feet per day in winter.
HEX is also working with Tyonek Native Corporation and Cook Inlet Region, Inc. to drill for an onshore oil play.
Alyeschem broke ground on the first petrochemical plant in the US Arctic in late May. The North Slope factory will manufacture value-added chemicals and fuel products, such as ultra-low sulfur diesel. “What we’re doing with Alyeschem is creating a plant to make methanol and to desulfurize diesel. This is something that almost every chemical engineer who’s gone through the North Slope for the last forty years has known that would be useful,” said Alyeschem COO Craig Graff in May.
Alyeschem anticipates reducing the carbon dioxide emissions of North Slope operators by 93 percent—approximately 45,000 tons per year—compared to current supply methods. The facility will likely also eliminate an estimated 4,000 truck trips annually, reducing road wear and emissions across the region.
The company finished driving pile for the project in late summer, and the next step is trucking up additional material. Alyeschem expects to come online in late 2027, and the company will create approximately fifteen operations jobs.
This summer the Alaska legislature failed to pass a much-anticipated tax structure that, in May, the company called a “critical condition.” Glenfarne named a second critical condition in May, that the Regulatory Commission of Alaska (RCA) approve and formalize what is currently a nonbinding agreement with ENSTAR to supply the utility with gas for thirty years. “We’ve had to come up with an arrangement with ENSTAR that shows you and everyone that we can deliver gas from the North Slope that’s more reliable and more cost-effective than importing LNG,” said Brendan Duval, CEO of Glenfarne. “We’re about to put finishing touches on that agreement so it can go through the RCA.”
In better news for the project, in September President Donald Trump announced South Korea’s intent to invest in Alaska LNG, but South Korean officials explained a decision on whether to invest or how much is not final. Earlier this year South Korean officials said an investment required more offtake agreements than the 13 million tons per year the project currently has. Glenfarne needs to secure agreements for approximately 3 million more tons per year.
Nonetheless, the conversation between government officials is a positive sign of interest in the project. If the agreement is formalized at a later date, it would likely give South Korea favorable conditions for Korean-made equipment, including tariff relief on steel; long-term LNG purchase agreements on economically viable terms; priority access to Alaska LNG; and protections for Korean investors.
While Alaska LNG remains one of the most promising projects on Alaska’s horizon, it’s likely that this year will close out without a final investment decision.