laska’s mining industry remains a major contributor to the state’s economy, supporting jobs, local businesses, public revenue, and infrastructure development. Its reach extends from long-established gold operations around Fairbanks and zinc and lead mining in the Brooks Range to emerging critical-mineral projects in Southcentral. Together, these activities illustrate both the scale of Alaska’s mineral resources and the range of conditions under which development occurs.
As 2026 closes, here’s a regional look at Alaska’s mining production, ambitious exploration programs, and major projects moving through the state’s permitting and development process.
In September, the Federal Permitting Improvement Steering Council welcomed the Red Dog Mine Life Extension Project to FAST-41, an accelerated federal review process for major infrastructure projects. “Alaska’s extraordinary critical mineral resources represent a tremendous opportunity to strengthen US national and energy security,” said Emily Domenech, Permitting Council executive director. “After supporting the Red Dog Mine’s Aqqaluk Pit expansion through federal permitting, we’re excited to ensure this critical mine life extension is permitted efficiently.”
The extension project will work to develop ore deposits through underground long-hole stoping mining methods. The deposits contain zinc, lead, silver, and germanium. The US Army Corps of Engineers will serve as the lead federal permitting agency for the extension project. Without expansion into new deposits at the Aqqaluk site, Red Dog faces a hard closure in 2031. New exploration in that area is meant to bridge the transition from an open pit into an underground mine at the undeveloped Aktigiruq and Anarraaq deposits, keeping Red Dog operating into the 2040s.
In July, Ambler Metals received a coordinated federal and state permitting schedule under FAST-41. “A clear, transparent permitting schedule benefits everyone, particularly the agencies conducting the review, the stakeholders following our progress, and the communities nearest this point,” said Ron Rimelman, president of Ambler Metals, a 50-50 joint venture of Canada-based Trilogy Metals and Australia-based South32. “We will continue to maintain that mining in the Upper Kobuk must be built on a foundation of lasting local support, and we will continue to prioritize deep engagement with nearby villages and regional stakeholders to ensure the Arctic Project delivers multi-generational economic growth and high-quality jobs.” A notice issued in September to draft an environmental impact statement for the open-pit mine formally triggered a 29-month permitting schedule.
Developers estimate that the Arctic Project would create 1,000 jobs in both construction and operations, $407 million in state revenue, and $60 million in wages per year. In September, the US Department of War secured a 10 percent equity stake in Trilogy Metals with a $35.6 million investment, supporting Ambler exploration for minerals needed for national security. However, commercial viability depends on construction of a 211-mile industrial road to the Dalton Highway. The road has a federal permit, but a land transfer is being challenged in court.
Governor Mike Dunleavy wrote an op-ed for Fox News in August describing the Graphite Creek project as a potentially significant domestic source of graphite as the United States seeks to strengthen critical mineral supply chains and reduce reliance on foreign sources. “Among its many mineral deposits, Alaska holds a bountiful reserve of graphite in the aptly named Graphite Creek project. New estimates suggest that this one reserve alone could provide enough graphite to meet the entire nation’s needs for a century,” Dunleavy wrote.
Graphite One—a publicly traded company with significant investments from Bering Straits Native Corporation, Aleut, and Doyon, Limited—continues to advance engineering, exploration, and permitting work. State records show a variety of permits covering exploration, water use, land use, and fish habitat. Currently, the project remains in the development stage. One of the earliest FAST-41 projects, Graphite Creek has progressed to a rigorous environmental impact statement.
A manufacturing facility in Ohio is targeted to open in 2028 before production begins from the open-pit Graphite Creek mine in 2029 or 2030.
DNR received requests to renew the Plan of Operations and Reclamation Plan Approvals for the Fort Knox Mine and Gil Project to support continued mineral extraction, development, processing, and reclamation. The renewal application includes state and private lands within the Fairbanks Mining District.
DNR released draft Plan of Operations and Reclamation Plan approvals in May, while the Alaska Department of Environmental Conservation released a draft waste-management permit addressing waste rock and water management. A public review and comment period ran from May 8 through June 7.
The plan was approved with effective dates of September 10, 2026, through September 10, 2031, unless sooner revoked. Kinross touts the Gil Project as a demonstration of how Alaska’s established mining infrastructure can support additional development without starting from scratch.
Kinross is also the majority partner in the Manh Choh gold mine approximately 10 miles south of Tok, a joint venture with Contango Silver and Gold. Mining began in 2023. Manh Choh ore is transported through Fairbanks to be milled at the Fort Knox processing facility.
In 2026, Contango continued production campaigns at Manh Choh and reported improvements at Fort Knox to accommodate higher-grade ore from the operation. The third campaign for 2026 from the Manh Choh mine began August 20. Modifications to recover higher-grade sulfide ore from the South Pit have been completed and implemented at the Fort Knox mill and are operating as planned.
Pogo’s 2026 regulatory activity included an April amendment to its Plan of Operations and additional permits addressing water and fish habitat issues. The mine’s existing infrastructure remains a major asset. Pogo has its own access road, camp, mill, power system, tailings facilities, and water-management infrastructure.
This year, Northern Star celebrated twenty years of operations at Pogo. During a keynote address at the April 2026 Alaska Miners Association’s Biennial Convention in Fairbanks, General Manager Mick Eckert told attendees that roughly one million feet of drill core passed through its Pogo core shack in 2025. A lower resource cut-off grade, driven by higher gold prices, also contributed to the substantial increase in resources.
In May 2026, Alaska released draft decisions on Hecla’s requests to renew its Reclamation Plan Approval and Waste Management Permit. The public comment period ran through July 1. DNR and the Alaska Department of Environmental Conservation completed their review and response to public comments, issuing the renewed Waste Management Permit effective from September 14, 2026, through September 15, 2031.
A tailings storage expansion is expected to extend operations through 2045, and Hecla is looking at its tailings piles for possible reprocessing. Preliminary work suggests it can glean more than 1 million more ounces of silver in the waste rock, provided a mill by NVRO Metals can proceed.
In May 2026, DNR approved an amendment to Kensington’s reclamation plan that modifies the Comet water treatment plant outfall. Kensington also has waste-management, air-quality, fish-habitat, and dam-safety authorizations.
DNR is currently overseeing the regulatory framework and adjudication process for Dawson Mine. The project is entirely on state-owned land. Because the mine lacks a federal nexus, state-level environmental and operational frameworks manage the permitting and authorization processes, accelerating standard development timelines.
The primary regulatory mechanism guiding the project’s current phase is the multi-year Revised Plan of Operations and Reclamation Plan. This comprehensive regulatory framework spans from 2024 through 2029, providing a structured pathway for the mine’s physical and economic expansion. In 2026, DNR’s oversight narrows to implementation of Phase 3 Operations, introducing critical updates to the mine’s blueprint, integrating new extraction methods, expanded localized processing facilities, and updated infrastructure to accommodate targeted gold-bearing ore.
Located approximately 125 miles southwest of Anchorage at the base of Mount Iliamna, the project targets high-grade deposits of gold, zinc, copper, silver, and lead. Contango Silver and Gold acquired the asset in 2024 by completing a buyout of HighGold Mining. Through the J T Mining subsidiary, exploration is proceeding on land leased from Cook Inlet Region, Inc.
The proposed operation would use underground long-hole stoping with backfilling to reduce the risk of surface subsidence. Under the direct-shipping ore model, the company would transport ore in containers rather than process it at an on-site chemical-processing or tailings facility. Contango is relying on a similar approach for its Lucky Shot project, which would revive gold mining in Hatcher Pass, pending a final investment decision expected in 2027.
Supporting infrastructure at Johnson Tract would include an industrial access road through national parklands, an expanded local airstrip, and a barge-loading terminal at Tuxedni Bay in Cook Inlet. The project is currently in the advanced exploration and permitting phase, with ongoing debate focused on potential environmental effects on local brown bears and endangered Cook Inlet beluga whales.
Permitting for the surface infrastructure, including the access road to the barge facility on the coast, remains firmly on schedule, the company reports. The team also completed geotechnical drilling within the easements for the road access and barge landing facility.
Equipment mobilization via barge and helicopter was successful, and the team completed on-site construction of the road from the camp to the proposed portal location. The portal pad is complete, and all surface site preparations for the underground exploration drift development have been completed on time and on budget.
Field surveys within Johnson Tract easements have been conducted in accordance with the Programmatic Agreement approved by the appropriate permitting authorities. Most environmental studies are substantially complete. These environmental and cultural baseline studies include marine and freshwater quality surveys; eagle, shorebird, and seabird surveys; marine mammal acoustics and fish surveys; wetlands mapping; and cultural resource studies.
Preparations and engineering design are also underway to substantially expand camp facilities in 2027.