Delta Backhaul, aided by local laborers, tidied up the 6.7-acre site, closing the majority of the old landfill through consolidation, compaction, and cover and developing a more manageable 1-acre site. All the better for Kivalina’s eventual relocation, whenever that massive effort takes place.
“This project will serve as a model for future landfill clean-up projects in rural Alaska,” Huntman says.
The Alaska Department of Environmental Conservation (DEC) inspected the Kivalina landfill in 2018, resulting in a poor score of 14 percent. That report helped prioritize efforts to rehabilitate the landfill.
More than forty years’ worth of accumulated garbage was packed into 5-cubic-yard super sacks and staged on the beach (below). Due to funding shortfalls, the sacks are stuck for the winter until they can be shipped to Seattle in the spring for final disposal and a regulated landfill.
An unofficial inspection at the conclusion of the rehab improved the score to 60 percent. Huntman says Delta Backhaul is working with DEC’s solid waste program to permit the current site and bring the score up to 70 percent.
As part of the project, Kivalina purchased a John Deere 544K wheel loader, which will be kept in the city garage for use by the landfill crew. Also, Summit Consulting Services of Anchorage is fabricating two 7-cubic-yard burn boxes, which will incinerate some trash and reduce its volume, extending the useful life of the landfill. That hardware is set to be delivered on the first barge of the spring.
While the relocation of Kivalina to higher ground is on hold, the village does have an evacuation road to escape the worst coastal storms. Once a new class III landfill has been established along the evacuation road, the current site will be fully closed out. Huntman explains that it will be covered with an additional 2 feet of dirt, re-graded to prevent ponding and erosion, and then seeded with vegetation, as if it were never there.